Timeline

01.01.2024

Project Start

(the project is set in motion; its total duration set to 36 months)
01.01.2024
01.02.2024

WP2 Start

Functional Requirements and System Architecture
01.02.2024
01.04.2024

WP3 Start

Hardware Development
01.04.2024
01.06.2024

WP4 Start

Software Development
01.06.2024
30.06.2024

WP2 Completion

30.06.2024
01.12.2024

WP5 Start

System Integration
01.12.2024
01.06.2025

WP6 Start

Citizens Lab
01.06.2025
30.04.2025 

WP5 Completion

30.04.2025 
01.12.2025

WP8 Start

Exploitation and Commercialization
01.12.2025
31.12.2025

WP3 Completion

31.12.2025
31.12.2025

WP4 Completion

31.12.2025
01.01.2026

WP7 Start

Pilot Implementation, ‘Living Labs’ and Capacity Building
01.01.2026
30.04.2026

WP6 Completion

30.04.2026
30.09.2026

WP7 Completion

30.09.2026
31.12.2026

WP8 Completion

31.12.2026
31.12.2026   

Project Ends

The PAVE-SCAN project completes!
31.12.2026